Phase 1 US$250M; Phase 2 US$1.24B
Build 2032–2034 at 55% construction value-added, then 6% of capex per year operating. Peak US$273M/yr · cumulative 2026–40 US$1.3B.
Straight-line distance from the project point to the nearest vertex of each network layer.
| Railway | 12 km | |
| Major highway | 211 km | |
| Transmission ≥230 kV | 215 km | |
| Pipeline | 293 km | |
| Port | Belledune | 0 km |
| Generating station | Point Lepreau (660 MW) | 318 km |
| City >50k | Moncton | 218 km |
| Sisson Tungsten-Molybdenum | Minerals & Metals | 195 km |
| Atlantic Canada E-Fuels | Clean Energy | 215 km |
| Mactaquac Life Achievement Project | Power & Utilities | 230 km |
| Port Saint John Optimization | Marine & Port | 293 km |
| Beacon Data Centres — Spruce Lake | Digital Technology | 296 km |
| Mactaquac Life Achievement Project | Advanced / FEED | US$5.1B – US$6.6B |
| Beacon Data Centres — Spruce Lake | Advanced / FEED | US$3.9B |
| Atlantic Canada E-Fuels | Early / concept | US$1.0B |
| Sisson Tungsten-Molybdenum | Advanced / FEED | US$600M |
| New Nuclear in New Brunswick | Advanced / FEED | not disclosed |
| Port Saint John Optimization | Advanced / FEED | not disclosed |
Open on the Dealbook map · Open the Infrastructure Atlas · Back to the register