Minerals & Metals · SK · #41 of 131 disclosed prospectus tickets

Loki Flake Graphite

Summit deal plate

50 ktpa, 30-yr life; PEA

At a glance

Proponent
Dawn Zhou (proponent)
Capex (as printed)
US$1.4B
Capex (US$, midpoint)
US$1.4B
Stage
Feasibility / permitting
Location
55.50°N, 105.00°W
Summit deal plate
Yes — in the 167-project prospectus pitched Sept 14–15 2026
Fast-track list
No MPO referral on record
Project location.

Modelled GDP contribution Modelled

Build 2030–2032 at 55% construction value-added, then 15% of capex per year operating. Peak US$264M/yr · cumulative 2026–40 US$2.4B.

US$0MUS$100MUS$200M2026203020352040

Connectivity · nearest existing infrastructure

Straight-line distance from the project point to the nearest vertex of each network layer.

Railway218 km
Major highway390 km
Transmission ≥230 kV309 km
Pipeline456 km
PortChurchill747 km
Generating stationGrand Rapids (MB) (479 MW)449 km
City >50kSaskatoon386 km

Nearest other projects

McIlvenna Bay CopperMinerals & Metals174 km
Wheeler River UraniumMinerals & Metals236 km
North Star Project (BECCS)Clean Energy266 km
PLS (Triple R) UraniumMinerals & Metals361 km
SRC Minerals-to-MagnetMinerals & Metals387 km

Also in Saskatchewan

Rook I UraniumUnder constructionUS$1.6B
PLS (Triple R) UraniumAdvanced / FEEDUS$1.2B
Prairie LithiumUnder constructionUS$881M
Covenant Energy (renewable diesel + SAF)Advanced / FEEDUS$653M
Boardwalk Lithium BrineFeasibility / permittingUS$600M
Project Titan (sulphate of potash)Shovel-readyUS$150M – US$900M

Open on the Dealbook map · Open the Infrastructure Atlas · Back to the register